The system can be configured to calculate a due date for submission production tasks and editorial tasks. Four due-date options can be used with production tasks. One option applies to editorial tasks.
Due-date calculations may be affected by a publication’s configured due-date preferences regarding calendar/working days and national holidays. See Allow for Non-Working Days when Calculating Due Dates and Define National Holidays for Task Due Date Calculation.
Depending on configuration, due dates may be calculated in two ways:
The four options for due-date calculation described below can be used independently or in combination.
The due date can be calculated in relation to the assignment date of the task.
When this option is used independently, the system calculates a due date at the time the task is assigned by counting forward a specified number of days from the assignment date. (A system administrator defines the number of days a task recipient is allocated to complete the task.)
When this option is used in combination with one of the target publication date options below, the system may adjust the task due date in order to meet, if possible, the due date calculated by the target publication date option. The specified number of days configured for this option is also used when the system calculates a scheduled Must Start By date for the task.
The calculation is affected by the settings for calendar/working days and national holidays.
This option may be used for production tasks and editorial tasks.
A target online publication date is manually set for each submission on the Production Details page. This date is specific to the submission.
When this option is used independently, the system calculates a task due date by counting back a specified number of days from the target online publication date. The system warns the user assigning the task if the calculated due date has already passed, so the user can manually adjust the date.
When this option is used in combination with other options, the date calculated for this option is used as the due date if it is earlier than any other calculated due date. The system warns the user assigning the task if the calculated due date has already passed, so the user can manually adjust the date.
For calculating a scheduled Must Start By date, the configuration for this option is combined with the specified number of days after assignment (if configured in the first option, above). If more than one target publication option is configured, the earliest Must Start By date calculated by the system displays in the Production Status Grid and is used to calculate any task slip value. (Task slip is explained later in this article.)
The submission’s target online publication date is not overridden when the submission is assigned to a Schedule Group. This option allows a publication to identify an earlier target date for individual submissions even when they are assigned to an issue or other Schedule Group.
The due date calculation based on this target date is affected by the settings for calendar/working days and national holidays.
This option is available for submission production tasks.
Note: The submission target online publication date setting allows a publication to give individual submissions an ahead-of-print publication date that may be different from the submission’s associated Schedule Group, if the submission is assigned to a Schedule Group.
The Schedule Group target online publication date is read from the controlling Schedule Group when the submission is assigned to the Schedule Group (or when the submission’s designated controlling group is changed). The task due date is calculated by counting back a specified number of days from the Schedule Group target online publication date.
When this option is used in combination with other options, the date calculated for this option is used as the due date if it is earlier than any other calculated due date. The system warns the user assigning the task if the calculated due date has already passed, so the user can manually adjust the date.
For calculating a scheduled Must Start By date, the configuration for this option is combined with the specified number of days after assignment (if configured in the first option, above). If more than one target publication option is configured, the earliest Must Start By date calculated by the system displays in the Production Status Grid and is used to calculate any task slip value. (Task slip is explained later in this article.)
The due date calculation based on this target date is affected by the settings for calendar/working days and national holidays.
Schedule Group target dates can be modified from the Manage Schedule Group folder, by users with the Manage Schedule Groups permission.
This option is available for submission production tasks.
Note: The Schedule Group target online publication date may be used to give a Schedule Group an ahead-of-print publication date.
The Schedule Group target publication date is the print publication date inherited from the controlling Schedule Group when a submission is assigned to it (or when the submission’s designated controlling Group is changed). The due date is calculated by counting back a specified number of days from the Schedule Group target publication date.
When this option is used in combination with other options, the date calculated for this option is used as the due date if it is earlier than any other calculated due date. The system warns the user assigning the task if the calculated due date has already passed, so the user can manually adjust the date.
For calculating a scheduled Must Start By date, the configuration for this option is combined with the specified number of days after assignment (if configured in the first option, above). If more than one target publication option is configured, the earliest Must Start By date calculated by the system displays in the Production Status Grid and is used to calculate any task slip value. (Task slip is explained later in this article.)
The due date calculation based on this target date is affected by the settings for calendar/working days and national holidays.
Schedule Group target dates can be modified from the Manage Schedule Group folder, by users with the Manage Schedule Groups permission.
A submission’s own target publication date is overridden when the submission is assigned to a Schedule Group (i.e., the submission target publication date and Schedule Group target publication date are synchronized). The new target date value is retained if the submission is subsequently removed from the Schedule Group.
This option is available for submission production tasks.
Information about production task due dates and potential impact on schedules may be configured to display in several areas.
The production status grid can include Must Start By dates and task slip figures. Task slip is a measure of how late an individual task type is running (past its Must Start By day or Must End By date).
Editor and Publisher roles with permission have access to an “At Risk” Submissions folder on the Production Tasks menu. This folder contains all submissions that have an associated schedule slip. Schedule slip is a measure of how late a submission is currently running based on all individual submissions task slip figures for associated production task assignments.
Go to PolicyManager > ProduXion Manager > Configure Submission Workflows and Production Tasks.
For more details on task configuration, see Configure Submission Production Tasks or Editorial Tasks.
To return to previous page click ALT + left arrow